06.U1.403: water damage repair

When:
July 31, 2024 – September 15, 2024 all-day
2024-07-31T00:00:00+02:00
2024-09-16T00:00:00+02:00

Water damage repair works by Construction are planned to start by 31 July 2024 and are aimed to be completed by mid-September (depending on external inspections of the works). We will keep you updated as works progress.

Monday, 05.08.2024: start  the drying works  on the side of Imaging & Optics Facility and a smaller corridor on the hallway.

Tuesday and Wednesday 05-06.08.2024: the demolition work will take place, therefore it is possible to notice sound and vibrations in the area around the showers.

Thursday and Friday 09-10.08.2024: the drying machines will be installed. The installation will need to work 2-3 weeks to get this area completely dry.